Technical details for Oil Fired AGA (Noted for site preparation)

Please note the site preparation must be carried out in full before the fitting of the cooker.

ALL OF THE ITEMS UNDERLINED MUST BE FULFILLED OTHERWISE THE COOKER WILL NOT BE COMMISSIONED JUST DELIVERED AND ASSEMBLED.

1. FLUE - The existing chimney to be lined using 5" flexible flue liner.Internal and external prefabricated flue to be 5" double insulated. (SM).

Flue may exit horizontally or vertically from the Aga. Flue centre is 18 3/8`` from the right edge and 2 ½ `` from the back of the Aga.

We strongly recommend that a verdette cowl is fitted to your existing chimney.

2. VENTILATION - The minimum air provision is to fit an air vent of not less than 10sq cm of free air directly from outside to the room in which the appliance is fitted.

3. FUEL - 28 second heating oil. Feed pipe to Aga is 10mm diameter.

Level differential Aga and fuel tank outletshould be at least 18'(457mm). Oil control valve can be sited on either side of the Aga but may be sited up to 5 feet away. Oil valve is approx 4`` wide. The oil supply must be ready to be turned on.

New regulations (BS5410) now state that all oil supply lines must be protected by a remote

Acting firevalve (65 degree KBB). The valve must be situated outside the building where the oil line

Enters the building, with the sensor near the Aga.

4. HOT WATER - All Agas with hot water facility MUST BE CONNECTED TO A GRAVITY FLOW SYSTEM (which must be indirect). Water pipes can exit from either left or right of the Aga.

The hot water tank must be sited no more than 18 feet away, otherwise heat efficiency may be lost.

Water pipe size is 28mm. Dimensions for flow and return pipes on application.

5. PLINTH - The cooker should be positioned on a level base of non-combustible material.

Recommended plinth depth is 26`` (traditional) 27`` (delux): width to be 38 7/8`` (two oven) 58 5/8`` (four oven) and height of plinth is optional.

6. FITTING - Installation is carried out by our experienced and trained fitters and the cost includes labour but not the cost of any vitreous flue pipe. We would expect to arrive to find a fully prepared site, i.e. flue/chimney is lined, the oil tank and feed pipe are in place, the water pipes are ready for a plumber to connect on the day. The base/plinth is ready and that there is oil in the tank. The cost of commissioning is £200+vat and an extra £50+vat for water if water pipes are within 1 metre from Aga our charges do not include flue materials, building, plumbing or oil installation work. Please not that the Aga comes in pieces and will be built on site.

The above site preparation details are to be used as a guide and must be used in compliance with local building regulations.

 



Technical details for Oil Fired Rayburn

Please note the site preparations must be carried out before the fitting of the appliance

1. FLUE - The existing chimney is to be lined using 5" flexible liner. Internal and external prefabricated flue to be 5" double insulated (SM). Flue may exit horizontally or vertically from the RAYBURN.

We recommend that an anti-down draught cowl be used. The flue box on a rayburn supreme is on the right hand side- other rayburns on either side.

We strongly recommend a verdette cowl be fitted to your existing chimney.

2. ELECTRIC SUPPLY - This applies only to RAYBURN SUPREME. The fan-assisted burner requires a 240-volt supply and is fused at 3 amps.

3. VENTILATION - A permanent air vent with a minimum effective area of 5" square (or the cross sectional area of the flue pipe, whichever is greater) should be provided.

4. FUEL - 28 second heating oil. Feed pipe to RAYBURN is 10mm.

The oil control valve is situated on the opposite side of the flue, but may be sited up to five foot away. It is approxatly 5" wide.

The fuel supply must be ready to turn on.

New regulations (BS5410) now states that a remote acting fire valve (eg, KKB) must protect all oil supply lines. The fire valve must be positioned outside the building where the oil enters the building, with the sensor near the Rayburn.

5. HOT WATER & CENTRAL HEATING - All RAYBURNS with hot water facility MUST BE CONNECTED TO A GRAVITY FLOW SYSTEM (which must be indirect) with a 40 gallon hot water cylinder.

Central heating models, if fully pumped, will still need a separate gravity flow pipe in case of pump failure. The Rayburn Supreme has a maximum b.t.u output of 40,000 which we suggest is equivalent to approximately 8 single radiators. It can only be controlled by timing the central heating pump.

The 100sq ft model is fully manual with no need for electrical connection a central heating system. It is capable of heating 4 to 5 single radiators (100 square feet).

Both models should be fitted with either a flow pipe or hot water cylinder thermostat to switch on pump if water exceeds a certain temperature.

Water pipes exit from the opposite side to the flue. The hot water tank must be no further than 18 feet away, otherwise heat efficiency may be lost.

Pipe size is 28mm. Dimensions for flow and return pipes on application.

Note that the central heating models will also supply domestic hot water.

6. PLINTH - The cooker should be positioned on a level base of non-combustible material. Rayburn supreme-depth to be 23" and the width to be 35" while Rayburn royal-depth to be 20" and width to be 33". The height is optional.

7. FITTING COST - Our experienced and trained fitters carry out installation and the cost includes labour, all copper and brass fittings, plumbing and fittings but NOT the cost of any vitreous enamel flue pipe. And a further £50+VAT for the water, providing the water pipes are beside cooker. We would expect to arrive to find a fully prepared site i.e. that the chimney/flue is lined, the oil feed pipe is ready, the water pipes are ready, the base/plinth is prepared and that there is an oil supply. The cost of commissioning is £200+VAT.

OUR FITTING CHARGE DOES NOT INCLUDE FLUE MATERIALS, BUILDING.